[ARCHIVED] ROAD PAVING

road paving.jpg

Road paving is complete on Queen Street and Hugo Lane. Drainage work has begun on Dalton Road, Abbott Lane, Sycamore Street, Locke Road and Bridge Street. Once complete, paving will begin. The paving on these roads should be complete by the end of September. The building of the sidewalks on the second half of Warren Avenue will begin the week of August 4th. LAWN REPAIR AND SEEDING WILL BEGIN ONCE THE PAVING IS COMPLETE - EARLY FALL. Thank you for your patience.