[ARCHIVED] 2/29 Update on Rail Trail Project

rail trail.jpg

The trail from Heart Pond to the Westford line will remain open until the work from Lowell to Heart Pond is complete. The DPW will continue to work on prepared excavated areas from the Lowell line to Pond Street for paving.  It is anticipated that paving of this section will occur in the second or third week in April. Paving is of this section expected to take about a week to complete. Once that paving is completed, pavement removal and regrading of the trail base will then move to the section from Heart Pond to the Westford line. This section is expected to be complete by early May. This approach will avoid closing the entire Chelmsford section of the trail at one time. Please remember that repairs are subject to weather conditions!